FAQ's

The LirIC Interconnector Project is a proposed new HVDC subsea electricity interconnector between the Belfast region in Northern Ireland and the Ayrshire region in Scotland.

The main parts of the project include:

Scotland

• One HVDC converter station located in Hunterston.
• One 320kV HVDC onshore cable circuit of approximately 3km that connects the converter station to the offshore cables at the landfall.
• One 400kV HVAC underground cable of approximately 2km that connects the converter station to the existing Hunterston East substation at Hunterston.

Offshore

One 320kV HVDC offshore cable circuit (two cables in a circuit) of approximately 142km from Hunterston, Scotland to Kilroot, Northern Ireland.

Northern Ireland

• One HVDC converter station located in Kilroot.
• One 320kV HVDC onshore cable circuit of approximately 3km that connects the converter station to the offshore cables at the landfall.
• One 275kV HVAC underground cable of less than 1km that connects the converter station to a new NIE substation adjoining the converter station location in Kilroot.

The Project will provide up to 700MW of further capacity capable of being transmitted in both directions between the Irish Integrated Single Energy Market (I-SEM) and the GB wholesale electricity market. LirIC is a unique project in that it will connect between the European and British electricity network but exists wholly within the UK. 

Increased interconnection between transmission networks results in a larger energy market enhancing grid stability, lowering energy costs, and facilitating the transition to renewable energy through cross-border trading. Developing a new interconnector with Great Britain is required both from the developer and societal perspectives. Furthermore, it supports the achievement of Ireland’s 2030 energy objectives and de-risks offshore wind development.

NI currently has one interconnectors, Moyle, allowing it to export and import electricity to and from Scotland, with the North-South interconnector, connecting NI to the Republic of Ireland (RoI) in the development stage, though much delayed.in . The Integrated Single Electricity Market (I-SEM) is also supported by the East West Interconnector between Wales and RoI. The need for further interconnection between the I-SEM and other markets has been recognised in several studies to date, in particular the need for further interconnection to Great Britain. 

Increased interconnection between transmission networks results in lower energy costs for consumers and businesses. More specifically, the overall benefits across Scotland, Northern Ireland and Republic of Ireland can be quantified as follows:

• 33TWh of reduced wind curtailment.
• 3m tonne reduction in carbon emissions.
• £912m in consumer welfare benefit in social Net Present Value (NPV) terms.
• £1.23bn socio economic welfare benefit (excluding the costs of LirIC) in NPV terms,
• £1.76bn system cost benefit (excluding costs of LirIC) in social NPV terms, which includes the wider benefit to society of decreased carbon emissions.

Specifically for Northern Ireland the benefits were estimated to be nearly £600m in socio-economic welfare benefit, positive (£150m) consumer benefits (from lower wholesale prices), reduced emissions and lower wind curtailment. 

For the onshore works in Scotland, the Project will apply to North Ayrshire Council for planning permission under the Town and Country Planning (Scotland) Act 1997 (as amended). For the onshore works in Northern Ireland, the Project will apply to Mid and East Antrim Council for planning permission under the Planning Act (Northern Ireland) 2011.

For the offshore works in Scotland, the Project will apply to the Marine Directorate - Licensing Operations Team (MD-LOT) for a marine licence. For the offshore works in Northern Ireland, the Project will apply to the Department of Agriculture, Environment and Rural Affairs (DAERA) for a marine licence. 

The project will take approximately 4 years to build, with the aim to be operational by 2032.

Any local disruption during construction will be minimised to ensure no significant impacts on local communities with comprehensive mitigation and management measures. For example, construction traffic and working hours will be managed using a Construction Traffic Management Plan that will be reviewed and approved by the Local Planning Authority.

A full Environmental Impact Assessment is being undertaken as part of the consent applications which will present any mitigation that will be incorporated into the construction management plans. Any construction and operational noise will be subject to rigid control and mitigation measures in compliance with industry construction standards such as BS 5228 and BS4142.

Employment creation is expected to be at its maximum level during the construction phase of the project where it is expected there will be approximately 500 full time roles. During the operational phase, there are expected to be around 10 full time roles as part of the ongoing operation and maintenance of the interconnector.

Electricity interconnectors enable the efficient integration of renewables onto the system. Interconnectors enable the efficient utilisation and integration of renewables onto the system by:

• providing a route to maximise renewable use through exporting or importing renewable electricity;

• making renewables, such as wind generation, more investable through helping to support the maximisation of revenues; and

• as more inherently unpredictable renewable generation is connected to the system, providing the flexibility needed to support the system operator to balance supply and demand and reduce the need to curtail excess renewable generation.

Interconnectors also help to deliver and strengthen security of supply by supporting the diversification of generation being imported and enabling neighbouring countries to support each other when domestic energy does not meet demand.

The converter station will comprise large warehouse-type buildings and outside electrical equipment. The total converter station footprint will be approximately 240m × 120m in size with buildings up to 23.8m in height, to accommodate the equipment needed.

We will also need temporary construction areas, and underground cables to connect the converter station to the existing substation. Our plans will include landscaping and to help screen the site, reduce its visual effects and increase biodiversity. 

Transmission Investment (TI) is a UK-based, leading independent electricity transmission business, with over 15 years’ experience developing, acquiring, and managing large complex infrastructure projects. In 2025, the Abu Dhabi National Energy Company TAQA, one of the largest listed integrated utilities companies in Europe, the Middle East and Africa, announced that it had acquired 100% of Transmission Investment.

This development and construction is being entirely funded by Transmission Investment, supported by TAQA. We recover our costs through transmission charges during the operational phase levied by National Grid. The amount we are able to recover is agreed with Ofgem, which is committed to working with industry, governments and consumer groups to deliver a net zero economy at the lowest cost to consumers. 

The LirlC interconnector will be designed to have a working life of 50 years from the date of commissioning.

Any local disruption during construction will be minimised to ensure no significant impacts on local communities with comprehensive mitigation and management measures. For example, construction traffic and working hours will be managed using a Construction Traffic Management Plan that will be reviewed and approved by the Local Planning Authority.

Given that the project will be privately funded, the regulatory authorities use a funding model called Cap and Floor. Under this funding mechanism consumers underwrite the risks of developers not being able to recover costs (the floor), allowing the interconnector to continue to operate and consumers to enjoy the supply security and carbon benefits of the interconnector. In return, they also benefit when revenues exceed the cap and these revenues are transferred to consumers. They avoid downsides, including the burden on energy bills of the construction cost, the risk of cost overruns, start-up delay and future repair costs.

In GB Ofgem has supported a Cap and Floor mechanism and we are working with the NI regulatory authorities to develop a Cap and Floor mechanism in that jurisdiction.

Developing a Cap and Floor regime in NI would support investor confidence in building greater interconnection across the UK. This will accelerate the delivery of social economic welfare benefits to UK consumers - avoiding disadvantaging UK interconnection projects compared to our EU neighbours.

About

Mobirise Extensions